Perbandingan Tonase Kemajuan Tambang Menggunakan Metode Mine Survey Terhadap Realisasi Penambangan di Bukit Everest PT. Antam Tbk. UBPN Sulawesi Tenggara
DOI:
https://doi.org/10.33379/gtech.v8i1.3789Keywords:
Mine Survey, Realisasi penambangan, Tonase BijihAbstract
Mount Everest, one of PT's mining areas. ANTAM Tbk. UBPN Southeast Sulawesi. To find out the actual mining tonnage, it is done in two ways, namely the weighing method and the truck counting method. The weighing method is applied to high-grade saprolite ore (HGSO) material with Ni content ≥ 1.80%, while the truck counting method is applied to two materials, namely low-grade saprolite ore (LGSO) with a content of 1, 50% ≤ Ni < 1.80% and overburden material (OB). This survey was conducted to compare the actual mining tonnage with the mining progress tonnage using the Mine Survey method. Calculation of the tonnage of the mine survey using the Surpac 6.3 software. Based on the results of the calculations carried out, the difference in the tonnage produced between the mining realization using the mine survey method, namely high-grade saprolite ore and low-grade saprolite ore material, shows that the actual mining tonnage is larger than that of the mine survey method of tailings material is that determined by the mine survey method Tonnage higher than the mining realization.
References
Azis, A., Saismana, U., & Riswan, R. (2020). Evaluasi Pencapaian Target Produksi Penambangan Berdasarkan Metode Survey Dan Truck Count Di PT Jhonlin Baratama Site Kintap. Jurnal Himasapta, 4(3). DOI: https://doi.org/10.20527/jhs.v4i3.1358.
Jekson. 2017. Studi Teknis Penambangan Bijih Nikel Pada PT. ANTAM Tbk. UBPN SULTRA. Laporan Kerja Praktik. Diakses melalui Perpustakaan Fakultas Sains dan Teknologi Universitas Sembilanbelas November Kolaka.
Muhlis. 2018. Kecamatan Pomalaa Dalam Angka 2018. (2019 Maret 4). Diakses dari https://kolakakab.bps.go.id/publication/2018/09.
Muliadi, M., Anshariah, A., & Jafar, N. (2018). Pemetaan Kemajuan Penambangan pada Pit X Daerah Morowali Provinsi Sulawesi Tengah. Jurnal Geomine, 6(1). DOI: https://doi.org/10.33536/jg.v6i1.181.
Resyani. 2018. Studi Teknis Pengeboran Eksplorasi Detail di Tambang Utara Pada PT. ANTAM Tbk. UBPN Sulawesi Tenggara. Laporan Kerja Praktik. Diakses melalui Perpustakaan Fakultas Sains dan Teknologi Universitas Sembilanbelas November Kolaka.
Sahrul, S., & Astini, V. (2020). Analisis Deformasi Lereng Menggunakan Metode Monitoring pada Lereng Jalan Trans Provinsi Kilometer 18 Kolaka Provinsi Sulawesi Tenggara. Jurnal Geomine, 7(3), 189. DOI: https://doi.org/10.33536/jg.v7i3.422.
Salu, S. P. Rancangan Tahapan (Pushback) Penambangan Endapan Bijih Nikel Pada Pt. Hengjaya Mineralindo (Hm) Kecamatan Bungku Pesisir Kabupaten Morowali Provinsi Sulawesi Tengah. https://doi.org/10.17605/OSF.IO/35YGW.
Suhairi, R., Nurhakim, N., & Riswan, R. (2018). Evaluasi Kemajuan Tambang Bulanan Berdasarkan Metode Survey Pada PT XYZ. Jurnal Geosapta, 4(01). http://dx.doi.org/10.20527/jg.v4i01.4509.
Suparlan, M. 2017. Studi Teknik Penambangan Endapan Bijih Nikel Laterit Di Blok IV Pit 1 Pada PT. Indoberkah Jaya Mandiri Desa Tanda Oleo Kabupaten Morowali Kecamatan Bungku Pesisir Provinsi Sulawesi Tengah. Laporan Kerja Praktik. Diakses melalui Perpustakaan Fakultas Sains dan Teknologi Universitas Sembilanbelas November Kolaka.
Ulang, MS. 2017. Analisis Kemajuan Tambang Nikel. Strata 1 Skripsi. Diakses melalui Perpustakaan Fakultas Sains dan Teknologi Universitas Sembilanbelas November Kolaka.
Downloads
Published
Issue
Section
License
Copyright (c) 2023 Sahrul Poalahi Salu, Chanro Silaban

This work is licensed under a Creative Commons Attribution 4.0 International License.